Godrej Vanantara Construction Status
Godrej Vanantara's construction status is in the early site-preparation stage (RERA-approved 13 May 2026, Project Start Date 15 May 2026) and will begin after its official launch (15 May 2026). In the current stage, the site clearing, land levelling, and boundary preparation are underway as per the RERA-filed Project Schedule. Internal access roads and security infrastructure will be set up in the coming weeks.
The township's development time period is set for 5 years from the date of launch. Its completion and possession date is 31st December 2031. The development of towers, amenities, and other parts of the township will begin after launch.
The construction timeline of the township is mentioned below:
- Pre-Launch Date: 12 May 2026
- Launch Date: 13 May 2026 (Project Start Date: 15 May 2026)
- Completion Time: 5 Years
- RERA Proposed Completion Date: 31 May 2031
- Possession Date: October 2031