Godrej Bannerghatta completion date

Featured Image of Godrej Bannerghatta completion date

The completion date of Godrej Bannerghatta is planned for 31 May 2031, with possession date scheduled for October 2031. The building work of this new project will start after the official launch date in May 2026. It is expected to take about 5 years to complete the full project. Buyers can expect to move to their flats by the end of Oct 2031, based on the builder’s plan.

Completion date is the stage at which the construction work, including towers, flats, and common spaces, is expected to be finished. It helps all the buyers understand when their homes will be ready to move.

The completion date of Godrej Bannerghatta is given now itself by the builder to ensure timely delivery. Buyers can track the latest updates of this project on the Godrej Properties website or the Karnataka RERA portal, as it shows the approved project timelines.

Key Dates


  • Pre-Launch Date: 12 May 2026
  • Launch Date: 13 May 2026
  • Project Duration: 5 Years
  • Completion Date: 31 May 2031
  • Estimated Possession: October 2031

Construction will start soon after the launch. The construction is split into many phases and all of these will be ready by the given completion date.

Project Construction Timeline


The sub structure of the project has the following timeline,

Project Work From Date To Date
Earth work and other leveling preparation work 15-05-2026 13-09-2027
Foundation footing work 11-11-2026 02-12-2027
Up to Plinth Level 12-12-2026 09-07-2028
Sub-structure flooring 09-06-2028 09-06-2029
Retaining wall 27-12-2026 08-08-2028

The super structure of the project has the following timeline,

Project Work From Date To Date
RCC or MS Framed structure 09-06-2028 02-10-2029
Masonry Construction 07-10-2028 31-03-2030
Plastering inside , outside & Ceiling 06-11-2028 27-09-2030
Joinery: Doors, Windows, Ventilators etc 04-02-2029 14-06-2030
Basic work of Water supply, Sanitary and Electrification 21-11-2028 31-01-2031
Dadoing, Skirting, Flooring, Tiles work (All types) 05-01-2029 14-06-2030
Railing and Grill fixing 21-11-2028 30-03-2030

The timeline for finishing works are as follows,

Project Work From Date To Date
Electrification, Water supply and Sanitary Finishing 21-03-2029 30-04-2031
Painting 20-04-2029 09-03-2031
Fire prevention fitting and fixture with network 21-03-2029 30-04-2031
Weather Proof work (tile,concrete) 05-04-2029 21-12-2030
Wardrobe, Showcase, Kitchen cabinet, Puja work
Elevation work 20-01-2029 20-04-2031
Internal and External work including landscapes as per sanctioned drawings 18-06-2029 31-05-2031

The completion date is important for everyone because it helps buyers plan their home loans and moving schedule. Buyers can stay updated through the official project updates, and developer announcements to know all the step by step procedure till the completion date of for Godrej Bannerghatta.

Godrej Properties Prelaunch Project is Godrej Vanantara.

FAQs


1. When will the construction work of this project begin?

The main building work begins after the official launch in May 2026. Initial site preparation will take place before the full work starts.

2. What is the official completion date that is given for Godrej Bannerghatta?

The project completion is planned for 31 May 2031, with possession by Oct 2031.

3. Why is the completion date important for buyers?

It will help buyers to plan their finances, moving ideas, and home loans.